Dear VSC users,
Because of work required to add power supply and water cooling to the new MUSICA system we will need several downtimes of VSC-4 and VSC-5 in week 38 (16.9-19.9.):
Monday 16.9.2024: shutdown of all compute nodes (CPU+GPU) of VSC-4 and VSC-5 / from 09:00 to 13:00
Wednesday 18.9.2024: shutdown of GPU nodes (A40 and A100) and cascadelake nodes only / all day
Thursday 19.9.2024: shutdown of GPU nodes (A40 and A100) and cascadelake nodes only / all day
Please note that running jobs will be aborted. Access to login nodes and your data will be possible.
The previously announced downtime where we will make the clusters available for strong scaling tests (email from 18.7.2024) will take place at a later time.
Best regards,
VSC team